Financial Model of 200 MW Solar Park

[Source – SOLAR QUARTER, Date – 19th July, 2017] See Link

On 10th May , the lowest bidder for the solar park in Rajasthan had quoted Rs 2.62 per unit for Bhadla Solar Park phase IV and after two days, on Friday May 12th, ACME Solar Holdings quoted lowest solar tariff at Rs.2.44/kWh for 200 MW followed by Japan's SBG Cleantech One at Rs.2.45/kWh for remaining 300MW during an auction carried out by Solar Energy Corporation of India Limited (SECI) for 500 MW capacity in Bhadla Phase-III Solar Park, Rajasthan. The solar park is being set up by Saurya Urja Company of Rajasthan Ltd, a joint venture between Rajasthan and IL&FS Energy Development Company Ltd. Respectful players like Acme, SBG, Vinnet Mittals – Avada, Hero, Renew Power, Shapporji Palonji etc participated in the bid and it is really heartening and charismatic to see that LCOE of Rs. 2.44 per kWh is not only a finance game but a big game of technology as well.

The projects are likely to be completed in about 12-13 months.

The quoted tariff is fixed for 25 years with no escalation and the bidders have sought no VGF (viability gap funding) from the government.

The entire solar power will be consumed in Rajasthan, and power sale agreement with the state distribution companies is already tied up.

The developers are responsible to connect to the pooling sub-station of solar park. The developers will be paying solar park charges of Rs 45.2 lakh per megawatt towards land, connectivity (from pooling substation to state network) and other infrastructural facilities.